A project manager has been assigned to a hybrid project. The project manager needs to ensure all team members are collaborating and are aware of the project's ongoing changes.
What should the project manager do?
#61
Answer: A✅ Correct❌ Incorrect
A project leader is assigned to a new project and is asked to assemble an effective five-member agile team. If the project leader has no restrictions, which team should they choose?
#62
Answer: A✅ Correct❌ Incorrect
A project manager is leading the first agile project for the organization. During the kick-off meeting, the project manager notices that the team does not have the same understanding about agile approaches. The project manager is concerned about the impact of that confusion.
What should the project manager do to address this situation?
#63
Answer: B✅ Correct❌ Incorrect
A project manager is managing a construction project that is facing challenges. There is schedule overrun, cost overrun, and the client is unhappy with the specific scope progress.
What should the project manager do first?
#64
Answer: A✅ Correct❌ Incorrect
A project manager is planning a project with multiple work packages. Each work package has its own defined scope, but funding will be at the project level.
How should the project manager determine if the allocated resource budget is sufficient to cover the resource costs of the project?
#65
Answer: A✅ Correct❌ Incorrect
After a project team has been working on a project for several months, the project is cancelled. The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.
How should the project manager handle this situation?
#66
Answer: D✅ Correct❌ Incorrect
A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.
What should the project manager do first?
#67
Answer: A✅ Correct❌ Incorrect
A self-organizing team for a critical project is consistently delivering value according to their commitments. During a retrospective, the project manager observed that most of the team members were stressed due to over commitments.
What should the project manager do?
#68
Answer: A✅ Correct❌ Incorrect
A project manager works for a company that has a reputation of delivering environmentally sustainable projects. During the half- yearly review of the project, the project manager raises serious concerns with the project sponsor regarding the project's viability and success. There are some stakeholders who oppose this project on the grounds of compromising land erosion.
What should the project manager do?
#69
Answer: C✅ Correct❌ Incorrect
A project manager is assigned to a project with a long time line and complex scope. The client requires a high-level, long-term plan as well as something that will work immediately, adding features to the product as the project progresses.
How should the project manager plan and deliver this project?
#70
Answer: A✅ Correct❌ Incorrect
A project manager is in charge of a software development project. A key stakeholder complains that they never received the functionality test status reports. The project manager provides the reports, and the stakeholder notices that an important functionality for their area was not tested.
Which tool should the project manager have used to prevent this situation?
#71
Answer: C✅ Correct❌ Incorrect
A team is not delivering the committed work. Cards are not moving on the kanban board, and the burndown chart shows that the sprint progress is slow.
What should the agile project manager do?
#72
Answer: D✅ Correct❌ Incorrect
A project manager is asked to negotiate between two team members who frequently have misunderstandings in order to reach an agreement that will advance the project. What should the project manager to?
#73
Answer: D✅ Correct❌ Incorrect
A project manager is working on a project for a startup company. The company launched cloud-based agile project management and DevOps training modules via the learning platform to support multiple self-paced and virtual learning formats. In a recent sprint, the quality assurance team failed to thoroughly inspect the modules before deployment, resulting in a poor customer experience.
Which of the following issues is the project manager facing?
#74
Answer: B✅ Correct❌ Incorrect
A key challenge that a project manager is facing is the lack of discipline by various team members and their inability to harness energy to achieve the project objectives. What should the project manager do to overcome this challenge?
#75
Answer: A✅ Correct❌ Incorrect
A junior project manager was recently hired to lead a complex project scheduled to kick off in 2 weeks. The junior project manager was introduced to another project manager for mentoring.
Which two benefits will the junior project manager realize by being assigned to a mentor? (Choose two.)
#76
Answer: BE✅ Correct❌ Incorrect
A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall progress.
What should the project manager do next?
#77
Answer: C✅ Correct❌ Incorrect
During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager react to ensure the project remains successful?
#78
Answer: C✅ Correct❌ Incorrect
At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?
#79
Answer: B✅ Correct❌ Incorrect
A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other. What should the project manager do?
#80
Answer: D✅ Correct❌ Incorrect
An agile project team is creating an enterprise workflow system for a company. One of the project team members, who is the system design architect, keeps receiving telephone calls from the users who are asking questions about the system. The calls are impacting the architect’s daily work schedule.
What should the project manager do?
#81
Answer: D✅ Correct❌ Incorrect
A project manager has recently taken over a project and notices that a client team member often halts progress due to a lack of understanding of some project elements. The former project manager gave the new project manager a complete list of people to communicate with, and this client team member is not on it.
What should the project manager do?
#82
Answer: B✅ Correct❌ Incorrect
A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?
#83
Answer: D✅ Correct❌ Incorrect
An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented. This may require a significant change in the technical architecture and an additional release.
What should the project lead do first?
#84
Answer: B✅ Correct❌ Incorrect
Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.
What should the project manager have done to prevent this situation?
#85
Answer: A✅ Correct❌ Incorrect
Toward the end of a project, the project manager did not receive approval from a key stakeholder because the necessary deliverables were not functioning as expected. What should the project manager do next?
#86
Answer: B✅ Correct❌ Incorrect
A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?
#87
Answer: A✅ Correct❌ Incorrect
Due to a company merger and acquisition process, the main stakeholder of a critical project has been changed. This new stakeholder complains that they were unaware of a delay on the project of which the rest of the stakeholders were aware. All the communications about the project are shared via email at the start of every week.
How should the project manager address this situation?
#88
Answer: A✅ Correct❌ Incorrect
A client comes to the company asking to copy a project that was executed 2 years ago in the same city, with the expectation that the new project will have the same cost and duration. While finalizing the project management plan, the project manager realizes that the baseline costs are much higher than the original project.
What could the project manager have done to avoid this?
#89
Answer: C✅ Correct❌ Incorrect
A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the project?